Powering Commhoist & Redtrail

Cooler Unit Replacement

Case Study
26th November 2024

Project Overview: LIG delivered a complex and large-scale crane lift for our client, removing and replacing cooler units and installing …

Cooler Unit Replacement

Project Overview: LIG delivered a complex and large-scale crane lift for our client, removing and replacing cooler units and installing a new plant room.

Scope of Works:

Crane Specifications:

  • 650T mobile crane
  • 78.8m jib with a 60m radius and a Safe Working Load (SWL) of 7.8T.
  • Adapted crane configuration for decommissioning and installation phases.

Cooler Unit Removal:

  • Safely removed 6 cooler units, the heaviest weighing approximately 5T.

Installation Phase:

  • Installed a new plant room and cooler unit at height.
  • Coordination with the client to confirm lifting points and required equipment.

Operational Considerations:

  • Crane and transport setup blocked key loading bays, necessitating efficient scheduling.
  • Recommended a consolidated work plan to complete tasks in a single phase, avoiding extended disruption.