Project Overview:
LIG successfully installed three high-powered EVC chargers, overcoming logistical and site-specific challenges to deliver a seamless project on a public highway.
Scope of Works:
Charger Installation:
- Installed 3 x 150kW SWARCO chargers delivered from LIG’ stores.
Equipment Logistics:
- Collected GRP housing from DHL Rugby.
- Retrieved Transformer, RMU, and LV Pillar from HS&L for installation.
Site Preparation:
- Positioned equipment on the public highway; clearance and permissions secured in advance.
- Deployed two temporary pedestrian crossings for safe public access.
- Conducted letter drops to inform residents.
Traffic Management:
- Used no-parking permitted cones to ensure clear access to the site.